    Tariff Order for Utilities/licensees

    DATE & PETITION NO. ORDERS DOWNLOAD
    10.08.2022 & 5/2022 Hearing Order on Review Petition filed by APGCL for Review of NRPP’s Tariff Order dated March 21, 2022 regarding Tariff Order for FY 2021-22 and MYT Order for Control Period from FY 2022-23 to FY 2024-25
    10.08.2022 & 4/2022 Hearing Order on Review Petition filed by APGCL for Review of APGCL’s Tariff Order dated March 21, 2022 regarding Truing up for FY 2020-21, Annual Performance Review for FY 2021-22 and Annual Revenue Requirement of MYT Control Period from FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23
    21.03.2022 & 12/2021 APDCL - True-Up for FY 2020-21, APR for FY 2021-22, ARR for FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23
    21.03.2022 & 10/2021 NRPP - Approval of Capital Cost, ARR of FY 2021-22, ARR for Control Period from FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23
    21.03.2022 & 09/2021 APGCL - True-Up for FY 2020-21, APR for FY 2021-22, ARR for FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23
    21.03.2022 & 08/2021 SLDC - True-Up for FY 2020-21, APR for FY 2021-22, ARR for FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23
    21.03.2022 & 07/2021 AEGCL - True-Up for FY 2020-21, APR for FY 2021-22, ARR for FY 2022-23 to FY 2024-25 and Tariff for FY 2022-23

    Order for Renewable Energy

    DATE & PETITION NO. ORDERS DOWNLOAD
    23.11.2022 & 09/2022 Hearing Order on petition Petition submitted by M/s Purshotam Northeast Pvt. Ltd & M/s Kilton Renewable Energy Pvt. Ltd seeking extension in the timelines of Financial Closure and Schedule Commissioning Date of the 20 MW (10 MW x 2) project, Direct MNRE and SECI to release VGF amount or declare EPC agreements have been frustrated, allow the Petitioners to terminate the project and direct APDCL to return the Bank Guarantee to the Petitioners
    11.10.2022 & 09/2022 Hearing Order on petition submitted by M/s Purshotam Northeast Pvt. Ltd & M/s Kilton Renewable Energy Pvt. Ltd seeking extension in the timelines of Financial Closure and Schedule Commissioning Date of the 20 MW (10 MW x 2) project, Direct MNRE and SECI to release VGF amount or declare EPC agreements have been frustrated, allow the Petitioners to terminate the project and direct APDCL to return the Bank Guarantee to the Petitioners

    Order for Fuel & Power Purchase Price

    DATE & PETITION NO. ORDERS DOWNLOAD
    No Orders Uploaded

    Other Orders

    DATE & PETITION NO. ORDERS DOWNLOAD
    17.12.2022 & 15/2022 Order on petition no.15 of 2022 filed by APDCL seeking approval for procurement of 495 MW power from 3x660 MW Neyveli Uttar Pradesh Power Limited (NUPPL), a joint venture between NLC India and Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited.
    28.12.2022 & 10/2022 Corrigendum to the order dated 14.11.2022 in Petition no.10 of 2022 filed by APDCL requesting to approve the FPPPA petition and pass needful orders to adjust the excess pass-through subsequently
    16.12.2022 & 13/2022 Order on Miscellaneous Petition filed by APDCL seeking amendment of the AERC (Electricity Supply Code) Regulations, 2017 with subsequent amendments
    14.11.2022 & 10/2022 Order on Petition no.10 of 2022 filed by APDCL requesting to approve the FPPPA petition and pass needful orders to adjust the excess pass-through subsequently
    07.11.2022 & 11/2022 Order on Miscellaneous Petition no.11 of 2022 filed by APDCL seeking in-principle approval for the roll out of Smart metering on prepaid mode as per the guidelines from the Ministry of Power
    11.10.2022 & 09/2022 Order on petition submitted by M/s Purshotam Northeast Pvt. Ltd & M/s Kilton Renewable Energy Pvt. Ltd seeking extension in the timelines of Financial Closure and Schedule Commissioning Date of the 20 MW (10 MW x 2) project, Direct MNRE and SECI to release VGF amount or declare EPC agreements have been frustrated, allow the Petitioners to terminate the project and direct APDCL to return the Bank Guarantee to the Petitioners
    20.08.2022 & 03/2022 Order on Petition filed by APGCL for amendment of Regulation 51.2(a) of the AERC (terms and Conditions for determination of MYT) Regulations,2021 on Normative O & M cost of 98.4 MW Namrup Replacement Power Project (NRPP).
    28.06.2022 & 06/2022 Order on miscellaneous application to direct APDCL to transfer at least 20% of the additional Return on Equity (RoE) allowed on account of conversion of Grant & Debt to Equity towards Pension Trust for the next control period FY 2022-23 to FY 2024-25.
    24.05.2022 & 02/2022 Order on miscellaneous petition filed by AEGCL for approval of creation of Sinking Fund in the name of the Self Insurance Reserve (SIR) at 0.1 % per annum of the total cost of the asset subject to the limit of 10% of the Gross Fixed Assets (GFA) from FY 2019-20 onwards.
    24.05.2022 & 13/2015 Order on petition filed by EIPL requesting for invocation of Section 11(2) of the EA'03 in view of the imposition of Section 11 of the EA'03 by GoA for running of EIPL plants.