    Tariff Order for Utilities/licensees

    DATE & PETITION NO. ORDERS DOWNLOAD
    20.12.2019 & 10/2019 Hearing Order on petition no. 10 of 2019 filed by APGCL
    19.12.2019 & 11,12/2019 Hearing Order on petition no. 11 of 2019 & 12 of 2019 filed by AEGCL
    19.12.2019 & 7,8, 9/2019 Hearing Order on petition nos. 7 of 2019, 8 of 2019 & 9 of 2019 filed by APDCL
    25.06.2019 & Review Order on the Petition No. 1 of 2019 for review of APGCL?s Tariff Order dated March 1, 2019 of the Commission on Truing-up of FY 2017-18, Annual Performance Review of FY 2018-19 and Multi Year Tariff for the Control Period from FY 2019-20 to FY 2021-22
    25.06.2019 & Hearing order of Review Petition no. 02 of 2019 filed on the order dated 1st march, 2019 in the matter of true up for FY 2017-18, APR for FY 2018-19, ARR for the control period from FY 2019-20 to FY 2021-22 and tariff for FY 2019-20 for AEGCL.
    06.05.2019 & Review Order on the Petition no. 01 of 2019 filed on the order dated 1st march, 2019 in the matter of true up for FY 2017-18, APR for FY 2018-19, ARR for the control period from FY 2019-20 to FY 2021-22 and tariff for FY 2019-20 for APGCL.
    06.05.2019 & Review Order on the Petition no. 02 of 2019 filed on the order dated 1st march, 2019 in the matter of true up for FY 2017-18, APR for FY 2018-19, ARR for the control period from FY 2019-20 to FY 2021-22 and tariff for FY 2019-20 for AEGCL.
    01.03.2019 & 15/2018 Tariff Order for True Up for FY 2017-2018, APR for 2018-19, ARR for FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - AEGCL
    01.03.2019 & 14/2018 Tariff Order for True Up for FY 2017-2018, APR for 2018-19, ARR for FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - APGCL
    01.03.2019 & 16/2018 Tariff Order for True Up for FY 2017-2018, APR for 2018-19, ARR for FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - APDCL
    01.03.2019 & 15/2018 Tariff Order for True Up for FY 2017-2018, APR for 2018-19, ARR for FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - AEGCL
    01.03.2019 & 16/2018 Tariff Order for True Up for FY 2017-2018, APR for 2018-19, ARR for FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - APDCL
    01.03.2019 & 18/2018 Approval of Capital Cost, APR for FY 2018-19, ARR for Control Period from FY 2019-20 to FY 2021-22 and Tariff for FY 2019-20 - LRPP

    Order for Renewable Energy

    DATE & PETITION NO. ORDERS DOWNLOAD
    14.10.2019 & Order on Average Pooled Power Purchase Cost [APPC] for the Financial Year 2019-20

    Order for Fuel & Power Purchase Price

    DATE & PETITION NO. ORDERS DOWNLOAD
    No Orders Uploaded

    Other Orders

    DATE & PETITION NO. ORDERS DOWNLOAD
    19.12.2019 & 06/2019 Miscellaneous Petition No. 06 of 2019 for concurrence on Procurement of 114.11 MW Power from 4 x 180 MW Mangdechhu Hydro Electric Project, Bhutan
    14.11.2019 & 06/2019 Miscellaneous Petition No. 06 of 2019 for concurrence on Procurement of 114.11 MW Power from 4 x 180 MW Mangdechhu Hydro Electric Project, Bhutan
    15.10.2019 & 05/2019 Order on Miscellaneous Petition No. 05 of 2019 for grant of Open Access during the Tea crop season (from April to November) with Contract Demand of more than 1 MW (from April to November) to Bateli Tea Company Limited (BTCL)
    04.09.2019 & 05/2019 Order on Miscellaneous Petition No. 05 of 2019 for grant of Open Access during the Tea crop season (from April to November) with Contract Demand of more than 1 MW (from April to November) to Bateli Tea Company Limited (BTCL).
    17.08.2019 & 04/2019 Order on Petition No. 4 of 2019 filed by Assam Power Distribution Company Ltd. in the matter of Petition for determination of Stranded fixed cost and Additional Surcharge (FY 2019-20) for Open Access consumers of APDCL.
    27.06.2019 & 03/2019 Order on Miscellaneous Petition No. 03 of 2019 for disruption of power supply since 13.05.2019 to Prag Bosimi Synthetics Ltd. (PBSL) plant and commercial losses caused.
    05.01.2019 & 19/2018 Order on sou-motu petition filed by APDCL for Non-compliance of the Order of the Commission